Updated Bridge St. Rehabilitation Project 7-30-2018

 

Bridge Street Project Logo

 Bridge St. Rehabilitation Project Plans: click here

August 1, 2018: 

The project continues to progress and we have recieved updated information on the project schedule, which can be downloaded here: Bridge Street Project Update 7-30-2018

July 10, 2018: 

The project has progressed and the detour route is in effect for the northbound lane. Northbound Bridge St. will be closed from Stan Eaton to Hickory. Please see the below brochure to view the posted detour route, which is expected to be in effect thorugh mid-August. 

May 29, 2018:

The project is moving along and is now ahead of schedule and an updated version is now avaliable here.

May 24, 2018:

The Bridge Street Road Project is progressing. Crews are still working south of Lindenwood and are planning to complete paving in this area ahead of the Memorial Day weekend. Please continue to drive carefully in this area, as crews will be working north of Lindenwood beginning in the weeks following Memorial Day.

April 20, 2018:

This week, the City met with the contractors and our engineers for a pre-construction meeting regarding the upcoming Bridge Street Rehabilitation Project. The first stage of the project will be in the area south of Lindenwood to the City limits, where work will begin as early as Monday, May 14th. The street will remain open to traffic, but there may be intermittent lane closures. Traffic rerouting will not begin until late June. Please stay tuned to our website and Facebook page for updates throughout the summer. We are looking forward making this a safe project and seeing these road improvements in downtown Linden! Project Schedule Updated (See Below)

 

Updated Schedule Final 7 30 2018