PROJECTS INFORMATION

This page serves as the central source for updates on the various projects happening within the City of Linden.

Projects will be updated as information becomes available. 


Genesee County Water Connection Project

The county connection to the City of Linden water system was completed on April 29, 2025. This connection changed our municipal water system from a groundwater supply to a surface water supply. This change in water source will significantly reduce the mineral content “hardness” of the water and should eliminate the need for private water softeners in most cases. Based on this change, we recommend that residents place their water softeners in the bypass position to determine if the new water supply meets their needs without additional treatment.


In addition to water quality improvements, residents should start noticing an increase in water pressure. Based on current data, system pressures have increased 7-12 psi throughout the community. The city plans to continue making incremental increases until satisfactory pressures are reached.


Lindenwood Neighborhood Project

The Lindenwood Project is considered complete at this time. City inspectors and staff will continue to monitor landscape repairs for settling and to ensure appropriate turf establishment in the spring.


2024 LINDENWOOD NEIGHBORHOOD IMPROVEMENTS PLAN SET


West Rolston Road Repaving Project

The West Rolston Road Project has been completed and is fully open to travel.


Linden Mills Rehabilitation & Redevelopment Project

Work continues on the Linden Mill Rehabilitation Project. Contractors are currently working on exposing and rehabilitating the original stone foundations on the east and south sides of the building. This portion of the project is proving to be a slow and tedious process as structural engineers carefully examine, design, and direct the appropriate repairs. This activity is expected to continue for many weeks as the contractor works to slowly expose and stabilize small sections of the foundation. This procedure is critically important to ensure the long-term structural stability of the building before proceeding with other rehabilitation efforts.


CLICK TO VIEW H2A ARCHITECTS FULL PROPOSAL

Mill Renovation Flyer from the Genesee District Library (GDL)


PLEASE CLICK TO READ PRESS RELEASE ISSUED JUNE 12, 2025

Latest Mill Building Elevation & Design Drawings


Mill Advisory Committee Information

This Committee was re-established in 2022 for the mission of gathering information to make recommendations to the City Council regarding grants, fundraising opportunities and priorities for work on the Mill Building, through the use of current plans, assessments and reports. During the March 9, 2023 meeting, Committee members unanimously approved moving forward a recommendation of request for proposal for expression and interest to the City Council. The Committee had fulfilled its mission and was allowed to dissolve.


ADDITIONAL RESOURCES:

Mill Building Survey Results

Architectural Assessment Report (2015)

Facility Evaluation Report (2017)


Mill Pond Dam Sidewalk

The Mill Pond Walkway Project is substantially completed. City staff and engineers are now working with the contractor to complete miscellaneous “punch-list” items to finalize the project. Additional electrical improvements are being planned for late fall or early spring.


ADA Amphitheater and Gazebo Overlook

The City of Linden is currently reviewing bids for the installation of an ADA compliant platform overlooking the amphitheater and gazebo at Kimble-Sharp Gazebo Park. If approved, the project will provide a safe viewing space for visitors that are unable to navigate the stairs and walkways into the amphitheater. Construction is expected to occur this fall or early spring.


Loose Annex Remodel Project

Starting in the fall of 2025, the south wing of the Loose Center, commonly referred to as the “annex” will be undergoing a major remodel. The project will include minor construction modifications to improve functionality of the space, new floor finishes, lighting and ceiling upgrades, bathroom improvements, and painting for the entire space. The project should be completed this winter.


W. Broad Street Rehabilitation

The City of Linden is working with the State of Michigan to schedule a road rehabilitation project on E. Broad Street from N. Bridge to Ripley Road. The project will include a mechanical milling and asphalt overlay of the entire roadway, maintenance, and/or reconstruction of underground structures as needed, and ADA improvements to sidewalk ramps and pedestrian crossings. There is an outside chance that the project may begin this fall, but indications are it will have a spring of 2026 start.


Emergency Standby Generators

City Council recently approved the purchase and installation of emergency standby generators for the Rolston Road and Byram Lake sewer lift stations. These generators will ensure that the stations have continuous power even during power outages. Emergency generators for our two remaining stations are planned in 2025.


Safe Routes to School Project

The Safe Routes to School Project along Stan Eaton Drive and Hyatt Lane started in late October. The intent of the project is to provide safe pedestrian connections to Hyatt Elementary from W. Broad Street and S. Bridge Street. Prior to the onset of cold weather, the contractor was able to install the new asphalt pathway along Stan Eaton between S. Bridge Street and Hyatt Elementary School. They also began working on the installation of new sidewalks along the east and west sides of Hyatt Lane to make connections to W. Broad Street. Unfortunately, early winter weather brought progress to a halt in the first week of December. The contractor is expected to return in early spring to complete the project. The new sidewalks and pathways are expected to be opened once construction is completed and the areas are relandscaped.


Underground Fiber Project

Surf Internet is currently in the process of installing underground internet fiber throughout the city for residential connection. The installation is complete is several areas of the community and will continue to be installed in remaining areas throughout the construction season. Click the link for additional information: Surf Internet Fiber Optic Coverage Map - Surf Internet


Storm Drain Clean Up

Did you know that the storm drains found in our roads, parking lots and yards drain directly into our local lakes and rivers? Storm drain systems are designed to quickly remove excess water runoff to prevent areas from flooding. However, this draining process also allows other foreign objects access to our waterways. How can you help? Take the time to clean up any excess yard fertilizer, grass clippings, leaves, trash and other pollutants from storm drain covers. Take precautions to prevent any soaps, oils, grease, dog waste or other contaminants from entering the storm system. These little efforts will help ensure the only thing entering our surface waters is rainwater!



(Updated: December 2025)

LINKS AND RESOURCES